California and other Western states are increasingly regulating data center water use even as the federal government looks for ways to accelerate their development, including on public lands. These parallel trends raise a practical question for developers and water suppliers alike: what does it take to secure water that is legally available, reliable through drought, and deliverable on workable terms?
This final installment in our data center series brings together our first post on water supply planning and our second post on local moratoria and Imperial County litigation. We turn from whether a project can obtain approvals to whether its proposed water supply can support operations—and consider what emerging state and federal policies may mean for future projects.
The essential diligence has four parts: the legal basis for service, drought reliability, delivery infrastructure, and allocation of costs and risks. Each requires decisions by both project proponents and water agencies. Although data centers have brought these issues into sharper focus, the same questions about water rights, supply reliability, and infrastructure arise in many other types of industrial development.
Is the Water Legally Available?
For projects relying on an existing supplier, identifying water within the supplier’s portfolio is not enough. Water rights, service area boundaries, district rules, and contractual limits may affect the supplier’s authority to serve a new industrial use. A developer proposing to convert agricultural land or water to industrial purposes must examine whether the use requires additional approvals or is restricted by supplier policies.
The pending verified petition against Imperial Irrigation District illustrates the distinction. The developer sought to meet data center cooling demand through agricultural land fallowing and existing service entitlements. IID disputes its obligation to provide service under that arrangement. Whether water historically served the land is not necessarily the same question as whether the developer is entitled to industrial service.
Other sources present their own constraints: groundwater use may be subject to SGMA allocations or adjudications; transfers may require water right changes; and recycled water service depends on available volumes and supplier commitments.
Under AB 2469, effective January 1, 2027, local approval of a new data center or an expansion increasing maximum peak water use requires a water supply assessment (WSA), among other conditions. But a WSA does not itself confer water rights or guarantee service.
Will the Supply Be Reliable During Drought?
Both developers and water suppliers must consider how a project’s demand fits within the system during dry years, not just in an average year. Agencies should evaluate existing service commitments, shortage priorities, and whether a major industrial load would limit their flexibility to serve other customers.
Peak cooling demand may coincide with extreme heat and high systemwide use. A supplier’s shortage contingency plan, not simply a developer’s annual demand estimate, can determine when deliveries might be curtailed and which customers bear reductions.
AB 2619 requires urban water suppliers to include data center demand in their water shortage planning. Beginning in 2028, AB 2469 also requires applicants to submit water scarcity plans addressing reductions and operating adjustments during increasingly severe drought. Both sides must consider whether those adjustments are realistic and how shortages affect the broader system.
Can the Water Be Delivered?
An adequate supply on paper is not meaningful without sufficient conveyance, treatment, and/or distribution capacity. Recycled water can raise similar issues, including dedicated pipelines or additional treatment. Water agencies must assess whether upgrades are feasible and compatible with other system priorities; developers need to know whether permits, rights-of-way, environmental review, and construction can be completed on the project’s schedule—and within the project’s overall budget.
Who Pays—and Who Bears the Risk?
Government Code section 65964.7, enacted through AB 2469, assigns data center applicants the full cost of required water conveyance, treatment, storage, and distribution improvements, as determined by the water supplier. This substantially allocates infrastructure costs to developers, but does not resolve the scope or timing of improvements, financial assurances, or how to address facilities that also benefit other customers.
Service reliability remains separate. Water agencies need to protect existing customers and maintain flexibility during shortages; developers need confidence that costly infrastructure will provide usable service. Those interests must be reconciled through service conditions, capacity arrangements, and allocation of interruption risk.
Early coordination—and experienced water supply counsel—can add value here. Assessing legal authority, identifying necessary approvals, and structuring service commitments before substantial investments are made can help both sides avoid disputes and keep feasible projects moving.
The Next Phase of Data Center Development
Recent developments point in different directions. Western states and local agencies are seeking better information and stronger supply assurances, while federal agencies are identifying opportunities to facilitate development. Water and power constraints will help determine which projects proceed.
In northern Nevada, the Truckee Meadows Water Authority generally requires developers to acquire and dedicate sufficient water rights, plus 11 percent for drought reserves, and pay for necessary facilities. Although not a new data center policy, it demonstrates how securing the underlying supply—not merely financing its delivery—can become a condition of growth.
Utah’s 2026 legislation requires qualifying new large data centers to report their anticipated water use before construction and actual water use annually after operations begin. Like California’s AB 2469 and AB 2619, the legislation reflects a growing emphasis on collecting better information about data center water demand to inform water supply planning and regulatory decisions.
Federal policy, meanwhile, is increasingly focused on facilitating data center development. Interior’s 2026–2030 Strategic Plan identifies growing AI data center demand among its infrastructure priorities, and BLM recently approved a data center near an existing solar facility in Nevada. A 2026 USGS study also examined opportunities to locate data centers near energy infrastructure on Western public lands. Notably, the study expressly excluded water availability, critical habitat, protected lands, and cultural resources from its spatial analysis, while acknowledging their importance. Although federal initiatives may facilitate access to land and energy infrastructure, securing water supplies and addressing environmental constraints can present more difficult, site-specific challenges. In the arid West, existing water rights, competing uses, and environmental protections may constrain the ability to develop new water supplies to meet new demand.
Cooling technology also complicates forecasts. Recent analysis from Lawrence Berkeley National Laboratory describes growing interest in closed-loop and dry-cooling systems that can reduce on-site water use but may increase electricity demand. Future siting decisions may increasingly require integrated evaluation of water, power, and cooling design.
In sum, federal initiatives may open opportunities, but state requirements and local conditions will likely determine what can actually be built.
Planning Ahead in a Changing Legal Landscape
Our first post in this series examined the water supply issues developers should address early in project planning. The second explored how unresolved water concerns can delay or derail development, including through local moratoria and litigation. This final installment brings those issues together against a changing legal and regulatory landscape. Neither new state requirements nor federal initiatives to facilitate development eliminate the need to establish legally available water, reliable service, and the infrastructure to deliver it.
For developers and water agencies alike, identifying those constraints and structuring workable arrangements before major permitting and investment decisions can reduce disputes, improve project planning, and help determine whether a promising proposal can and should proceed. As demand for water-intensive industrial development grows, the lessons from data centers will be equally important for other projects seeking to secure dependable water supplies in an increasingly constrained legal and regulatory environment.